Back to all NEP Funded Activities
Basics
Ediz Hook Restoration- Phase III
DIR_0037
The project site is located on the southern shore of Ediz Hook, a natural but degraded 3-mile spit on the Strait of Juan de Fuca that forms Port Angeles Harbor. This project represents the third phase of restoration efforts on Ediz Hook. The goal is to restore processes along 1,200 feet of Ediz Hook shoreline.
https://www.elwha.org/home.html
06/09/2023 4:19 AM

EPA Direct
NEP Project
Local

Completed
2010
2013
To zoom, hold down the Shift key and drag a rectangle.
Location Information
Classifications
  • Ecological Restoration - Ecosystem
  • Beaches and Marine Vegetation
  • Forage Fish
  • Salmon

  • Clallam
  • North Olympic Peninsula
  • Strait of Juan de Fuca
  • Legislative District 24

  • Habitat
Organizations
Lower Elwha Klallam Tribe
Michael Rylko rylko.michael@epa.gov

Related Activities
None provided
Reported Funding

Activity financials are reported by Federal Fiscal Year (Oct. 1 - Sept. 30).

$581,257
$581,257
$0

None provided

2009 Total
NEP Award Funding: EPA Direct $581,257 $581,257
Total $581,257 $581,257
Reported Expenditures

Activity financials are reported by Federal Fiscal Year (Oct. 1 - Sept. 30).

$581,257
$581,257
$0

None provided

2009 Total
NEP Award Expenditures: EPA Direct $581,257 $581,257
Total $581,257 $581,257